The City of White Salmon has given the go ahead to resume work on the Jewett Water Main Improvements Project. According to the City, Crestline Construction and city engineers and inspectors Anderson Perry have submitted plans that meet Washington’s COVID-19 requirements for restarting construction. Crestline will mobilize equipment and reset signage on Monday, then will begin work on side service water lines in the core downtown area. Work will start Tuesday on the south side of Jewett Boulevard from Estes to Main and continue through May 15, then continue on that side from Main to Garfield the week of May 18. Crews on the week of May 25 will move to the north side between Estes and Main. Detours and lanes closures are expected to be similar to those that were used prior to the shutdown of work.